Part of Workstream: evidence recovery. PRINCE2 Project Initiation Documentation — G0 Pack (originally wiki page 1004) was copied unchanged on 19 October 2026; this site stands alone, so evidence references are given as plain IDs (e.g. EV-0249). All PRINCE2 pages →
Page ID: 1004 · Title: PRINCE2 Project Initiation Documentation — G0 Pack · Evidence status: Not yet labelled — see the Editing Protocol · Version: 1.2.0 · Editing Protocol
About this page type → Read the Docs#prince2-pid
PID — summary — current baseline, 19 Oct 2026
Current baseline, 19 Oct 2026 (PM File v0.1). Where earlier sections on this page differ, this one governs; they are kept as history.
Highlight Reports monthly, plus HR-01 at this rebuild.
Checkpoint, Exception and End Stage Reports as templates until first used.
G0 approval test
Each PID complete enough to authorise the next stage.
Business Case still justified within tolerance.
Roles accepted.
Product descriptions and quality criteria adequate.
Risk, issue, change and communication controls in place.
Stage Plan, Work Packages and acceptance tests defined.
No open exception above PM authority without a decision.
Operational assurance baseline — 19 October 2026
This is a dated control addendum to the working PID; it does not authorise external correspondence, paid orders, legal steps, or a new project baseline. The 18 December 2026 G0 gate remains unchanged. The HubSpot audit found 305 tasks (201 NOT_STARTED, 48 WAITING, 21 IN_PROGRESS, 35 COMPLETED); 111 open tasks are flagged overdue, 72 open tasks have priority NONE, and 55 HIGH-priority open tasks are overdue.
Association gap: 70 tickets are currently in open pipeline stages; 27 tasks are directly associated with tickets. The documented TASK → WP ticket → PROJECT ticket → PROGRAMME hierarchy must be reconciled against live associations; the older P1 deal has task associations that do not substitute for work-package links.
Held communications: 22 HubSpot tasks mirror Gmail drafts whose subjects explicitly say DON’T SEND. Ten were quarantined on 19 October as WAITING / LOW with a review date of 26 October; 12 remain to classify. Original bodies, recipients, message IDs and draft links must be preserved. Nothing is sent by this control update.
Organisation hygiene: 125 company records include eight duplicate-domain pairs. Among 180 contacts, 172 have a blank textual company field; that alone does not prove the CRM association is absent. Inspect associations and preserve distinct people, cases and correspondence before any merge.
Deterministic artifact-recovery cycle
Trigger: every new reply, archive discovery, notice, deadline change or scheduled review starts a recorded cycle. Do not claim a six-hour cycle ran unless a run log or dated record proves it.
Capture: preserve the original artifact or message, source/reference, sender/custodian, received/sent date, exact attachments and metadata. Keep sensitive or privileged material out of public pages.
Catalogue: assign or confirm a stable Evidence Library identifier; record provenance, hash where available, preservation location, access restrictions and what the artifact does and does not establish.
Control: update the authoritative case ticket; associate the task to its work-package and project ticket where those records exist; set one accountable owner, a justified priority, the next action and a verified due date.
Accept: distinguish acknowledgement, substantive response, artifact received, search completed, no-records response, withheld/partial response and unverified lead. An acknowledgement alone never closes the work.
Escalate and learn: act the same day on a statutory/preservation threat; issue an exception when tolerance is forecast to be exceeded; record decision/lesson, next control date and evidence of completion.
Control rules: no automatic merge, deletion, sending, or completion changes to improve dashboard counts. Duplicate resolution requires review of associations and source context. The no-send quarantine is a safety state, not closure.
Page version & change log
Current version: 1.2.0
Version
Date (UTC)
Editor (human or agent name)
Change
Source / evidence
1.0.0
2026-10-18T15:20Z
Tab (for Sion Buckler)
Footer standardised; no content change
Editing Protocol, 18 Oct 2026
1.1.0
2026-10-19
GPT-6
Added 19 Oct operational assurance baseline and deterministic artifact-recovery controls
HubSpot audit and associations, 19 Oct 2026
1.2.0
2026-10-19T21:09Z
Tab (for Sion Buckler)
Added current baseline section (19 Oct 2026): Current PID summary and tailoring; earlier content kept
Sion Buckler, 21:59 BST 19 Oct 2026 (PRINCE2 update and PM File); sources: send-readiness list, 19 Oct WG letters, research cycle 14, task ledger