Change Control — Change Request Log & Form

page · 2026-10-18T18:20:02Z · from wiki page 5286

Part of Workstream: evidence recovery. Change Control — Change Request Log & Form (originally wiki page 5286) was copied unchanged on 19 October 2026; this site stands alone, so evidence references are given as plain IDs (e.g. EV-0249). All PRINCE2 pages →

About this page type → Read the Docs#prince2-change-control

Change Control — 19 Oct requests — current baseline, 19 Oct 2026

Current baseline, 19 Oct 2026 (PM File v0.1). Where earlier sections on this page differ, this one governs; they are kept as history.

IDChangeRaisedDate (BST)BaselineDecision
CH-012Free admin first; no spend or archive visits until free routes answeredSion18 Oct 23:40Cost; Plan T14Approved; implemented
CH-013One email per body, no cc/bcc; HMLR SAR + EIR together, OC2 only for refusalsSion19 Oct 00:46–00:48Communication; WP-05.AApproved; implemented
CH-014Send flywheel: Tab sends READY drafts after final check; inbox check before each; HubSpot updatedSion19 Oct 20:13Organisation; CommunicationApproved; starts 20 Oct
CH-015Debrief flywheel SOP; Cloudflare redeploys authorised for itSion19 Oct 21:59Work packages; ConfigurationApproved; run #1 under way
CH-016PRINCE2 set updated to 19 Oct; PM File v0.1 (PDF)Sion19 Oct 21:59Management productsImplemented 19 Oct
CH-017One redeploy of the email-archive Worker to show attachmentsTab19 Oct 21:46Configuration (email site)Approved under Sion’s 21:34 request

Open from 18 Oct: CH-009 (footer vs central log) and CH-011 (WordPress plan) — Sion to decide.

Change request log

IDChangeRaised byDate (2026, BST)Baseline affectedDecision / status
CH-001Formalise HubSpot as private execution ledger; wiki stays public indexPM1 OctDigital/data approachImplemented
CH-002October run as S0 Stage Plan / control registerPM1 OctS0 baselineImplemented
CH-003Dashboard rebased to 80 live HubSpot tasks (94 − 12 cancelled − 2 samples)PM5 OctReporting baselineImplemented
CH-004Widen scope to the whole Cedwyn Estate (~40 parcels)Sion18 Oct 16:41Scope; PBS 3.2Approved by Sion; in progress (estate run E1 done)
CH-005Evidence-first architecture: EV pages; claims cite EV, PENDING or HYPOTHESISSion18 Oct 16:47Quality; PBS 2Implemented (210 EV pages)
CH-006Terse pages; Read the Docs anchor instead of explanationSion18 Oct 16:58QualityImplemented
CH-007Update to Sion after every research cycle (6 h)Sion18 Oct 15:15CommunicationImplemented
CH-008PRINCE2 layer rebuilt to PRINCE2 7 compositionSion18 Oct 19:02Management productsImplemented 18 Oct; review TBC — Sion to confirm
CH-009Footer table on every page, or central Master Change Log only (I-006)Tab18 Oct 17:04Configuration managementOPEN — Sion to decide
CH-010Cost pages show costs only; add litigant-in-person time lineSion18 Oct 19:14Plan costsImplemented
CH-011WordPress plan upgrade for full agent access (R-010)Tab18 Oct 16:53ToolingOPEN — Sion to decide

Change request form

FieldEntry
CR IDCH-NNN
Raised by / date
Description
Reason (with source)
Baseline affectedscope / time / cost / quality / risk / benefit
Impact: time
Impact: cost
Impact: risk
Options
Recommendation
Decision authorityPM within tolerance; Executive beyond
Decision / date

Procedure

  • Capture → assess impact → propose → decide → implement → log here and in the Issue Register.
  • No change to an approved baseline without a decision recorded here.

Page version & change log

Current version: 1.1.0

VersionDate (UTC)Editor (human or agent name)ChangeSource / evidence
1.1.02026-10-19T21:10ZTab (for Sion Buckler)Added current baseline section (19 Oct 2026): CH-012 to CH-017; earlier content keptSion Buckler, 21:59 BST 19 Oct 2026 (PRINCE2 update and PM File); sources: send-readiness list, 19 Oct WG letters, research cycle 14, task ledger